Re-4A revamps construction plans

Re-4A revamps construction plans

THE REVISED plan for the school district's construction project, after new cost estimates showed that the original design would not be affordable.

Re-4A revamps construction plans

THE REVISED plan for the school district's construction project, after new cost estimates showed that the original design would not be affordable.
Re-4A building schedule

Asbestos removal will begin in June.
Demolition of the science/vo-ag building will begin early June.
Excavations and foundation work will begin around in early July.
Major structural installation (steel beams, trusses) by August.
August-October: The completion of the locker rooms and the two middle school classrooms connecting middle school to band room.
October-December: Completion of elementary classrooms and the breezeway connection to the cafeteria.
January-March 2014: The completion of the career and technical education center and new high school classrooms.
March-May, 2014: Completion of the exterior including landscape and sidewalks.
May-August 2014: Final construction phase.
September 2014: Ribbon-cutting ceremony to start the school year.